total slack of activities and schedule logic
View Single Post
08-04-2012, 05:58 AM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
My guess would be that the tasks with the large amount of slack are not directly driving their successors because they are not the only predecessor to the task.
Other things like constraints and deadlines also alter slack.