but from today to where i see the critical path starting, there is also a shortest duration isnt it? I am still not clear why from today to the start of future critical date there is no critical path.
can it be because i had assigned percentages to some future activities either 100% or less, where their predecessors was not complete? so in a way i overrode my previous logic of things due to field progress... |
|
#2
|
|||
|
|||
|
It's impossible for me to guess without seeing the project file. Projects with multiple network paths will not show all tasks as critical - only those that have zero slack. Did you add the Total Slack field as I suggested? What are the total slack values -- fairly small?
Do you have constraints in the project? Julie |
|
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
How to show critical task bars in different color?
|
ketanco | Project | 1 | 05-17-2012 05:17 AM |
change color of critical activity texts
|
ketanco | Project | 3 | 01-05-2012 06:36 PM |
| calculate multiple critical paths | ketanco | Project | 3 | 12-26-2011 09:29 AM |
Critical Path w/ 2 Calendars
|
AndreT | Project | 6 | 07-27-2011 11:22 AM |
| HELP! Rebuilt box & IRM lock out of critical docs | markcal | Office | 0 | 04-25-2010 11:45 AM |