Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 07-26-2012, 11:52 AM
ketanco ketanco is offline critical path starting in future Windows 7 64bit critical path starting in future Office 2007
Expert
critical path starting in future
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default critical path starting in future

Hello,
On my project when I was updating I discovered that the critical path is starting at a future date, although from now till that future date I also have many activities including the first critical activity's predecessors. Why dont I have any critical activities between now and till that future activity? Isnt critical path supposed to encompass the entire duration of the schedule?
Reply With Quote
  #2  
Old 07-27-2012, 03:36 AM
JulieS JulieS is offline critical path starting in future Windows 7 64bit critical path starting in future Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

No critical path does not necessarily span the entire project. Constraints, lag, lead, calendar changes can all have an effect on critical path.

Complete tasks are not on the critical path.

Add the Total Slack field to your view to see the amount of slack before a task becomes critical. The value may be very small.

Julie
Reply With Quote
  #3  
Old 07-27-2012, 04:35 AM
ketanco ketanco is offline critical path starting in future Windows 7 64bit critical path starting in future Office 2007
Expert
critical path starting in future
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

but from today to where i see the critical path starting, there is also a shortest duration isnt it? I am still not clear why from today to the start of future critical date there is no critical path.

can it be because i had assigned percentages to some future activities either 100% or less, where their predecessors was not complete? so in a way i overrode my previous logic of things due to field progress...
Reply With Quote
  #4  
Old 07-27-2012, 09:46 AM
JulieS JulieS is offline critical path starting in future Windows 7 64bit critical path starting in future Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

It's impossible for me to guess without seeing the project file. Projects with multiple network paths will not show all tasks as critical - only those that have zero slack. Did you add the Total Slack field as I suggested? What are the total slack values -- fairly small?

Do you have constraints in the project?

Julie
Reply With Quote
  #5  
Old 07-27-2012, 12:07 PM
ketanco ketanco is offline critical path starting in future Windows 7 64bit critical path starting in future Office 2007
Expert
critical path starting in future
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

i already had the total slack column. the slack values differ much, some are small some are big.

and yes there are constraints for future activites such as i assigned them % values
Reply With Quote
  #6  
Old 07-27-2012, 02:50 PM
JulieS JulieS is offline critical path starting in future Windows 7 64bit critical path starting in future Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

No, sorry. I mean task constraints other than ASAP or task deadlines. Do you have Task Constraints or Task Deadlines set?
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
critical path starting in future How to show critical task bars in different color? ketanco Project 1 05-17-2012 05:17 AM
critical path starting in future change color of critical activity texts ketanco Project 3 01-05-2012 06:36 PM
calculate multiple critical paths ketanco Project 3 12-26-2011 09:29 AM
critical path starting in future Critical Path w/ 2 Calendars AndreT Project 6 07-27-2011 11:22 AM
HELP! Rebuilt box & IRM lock out of critical docs markcal Office 0 04-25-2010 11:45 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:28 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft