Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #3  
Old 07-23-2012, 02:22 PM
lylel lylel is offline Change Resource Time vs. Duration when Updating Work column Windows XP Change Resource Time vs. Duration when Updating Work column Office 2010 32bit
Novice
Change Resource Time vs. Duration when Updating Work column
 
Join Date: Jul 2012
Posts: 2
lylel is on a distinguished road
Default

Thank you for the information, I tried this and it solved the part about the duration changing, but now the Resource percentage won't change, but I need it to change. So, for example, if I have a task for "Mike" set for 1 hour, the Resource Name column says Mike[13%]. If I change the task to 2 hours, I want that column to say Mike[25%], but it stays at 13%. Is there any way to fix this part too?
Reply With Quote
 

Tags
duration, resource, work



Similar Threads
Thread Thread Starter Forum Replies Last Post
updating status date and actual duration ketanco Project 5 01-27-2012 07:32 AM
Can I change the horizontal scrollbar to scroll smoothly rather than column by column carpat Excel 0 01-10-2012 09:34 AM
Change Resource Time vs. Duration when Updating Work column baseline duration of summary not updating. why ketanco Project 1 12-14-2011 09:07 AM
Work not changing duration benoldays Project 0 02-14-2011 08:21 PM
Duration changes fail to update work effort Panteledes Project 6 05-25-2010 02:27 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:16 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft