![]() |
#3
|
|||
|
|||
![]()
Thank you for the information, I tried this and it solved the part about the duration changing, but now the Resource percentage won't change, but I need it to change. So, for example, if I have a task for "Mike" set for 1 hour, the Resource Name column says Mike[13%]. If I change the task to 2 hours, I want that column to say Mike[25%], but it stays at 13%. Is there any way to fix this part too?
|
Tags |
duration, resource, work |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
updating status date and actual duration | ketanco | Project | 5 | 01-27-2012 07:32 AM |
Can I change the horizontal scrollbar to scroll smoothly rather than column by column | carpat | Excel | 0 | 01-10-2012 09:34 AM |
![]() |
ketanco | Project | 1 | 12-14-2011 09:07 AM |
Work not changing duration | benoldays | Project | 0 | 02-14-2011 08:21 PM |
Duration changes fail to update work effort | Panteledes | Project | 6 | 05-25-2010 02:27 PM |