Hi all
I didn't save a baseline in MS Project 2010 before I entered actual progress last week! If I save one today and then enter this weeks progress will that be ok? Also, do I need to set the status date to today before I enter any progress? Thanks Jo |
#2
|
|||
|
|||
![]()
If you save a baseline after tracking - the tracked data will be copied into the baseline fields -- so you will miss any variance against plan for those tasks.
If you need variance information (which most of us do), save either a full baseline now (before entering other progress) or a partial baseline if you don't have the fully developed plan. I hope this helps Julie |
#3
|
|||
|
|||
![]()
Hi Julie
Yes I need to look at variance. Will set a full baseline now. Presume I need to set the status date (after setting the baseline) to today's date, and then enter the progress this afternoon? Thanks for you're help Julie |
#4
|
|||
|
|||
![]()
You're welcome. You would want to set the status date if you are using the Update Project command and tracking a large number of tasks in that way. The status date is also helpful to move incomplete work from the past forward to the status date.
I hope this helps. |
#5
|
|||
|
|||
![]()
Thanks Julie for your guidance
|
#6
|
|||
|
|||
![]()
You're most welcome and thank you for the feedback.
Julie |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
ketanco | Project | 5 | 02-11-2012 07:24 AM |
some work was complete at my baseline | ketanco | Project | 1 | 01-25-2012 02:45 PM |
![]() |
fridos | Project | 2 | 05-11-2011 10:08 AM |
![]() |
poyns | Project | 1 | 05-27-2010 10:59 AM |
Entourage (Mac) - is it possible to import if I didn't export? | NJDevil | Misc | 0 | 01-19-2010 04:39 PM |