If you save a baseline after tracking - the tracked data will be copied into the baseline fields -- so you will miss any variance against plan for those tasks.

If you need variance information (which most of us do), save either a full baseline now (before entering other progress) or a partial baseline if you don't have the fully developed plan.

I hope this helps

Julie