Unwanted separation of bars, and actual bar not coming upto current date
Hello, two questions related to each other:
1) Whenever I want to update a task, first I enter its % complete. Then I update the current date of the project and then I go to Tools>Tracking>Update Project. For the tasks that are 0% its no problem and MS project pushes the start date to current date. But for the tasks I entered a % already, it splits the task which I don’t want. How can I prevent this separation, for tasks that are already started, when I update the project date?
2) Also, I want it to bring the black progress bar in the blue bar up to the current date automatically, when I am doing all these. How can I do that?
So far, since it is separating the tasks, I am first making actual and remaining duration as zero, then assign another actual and remaining duration, to make the bar continuous, but have to adjust actual duration manually in order to bring to the current data date. I want the actual duration (the black bar within the blue bar) to continue automatically from the start date up to current date.
And by the way there are no assigned resources to anything, so they are not affecting anything.
|