Old 06-27-2012, 09:20 AM
JulieS JulieS is offline Unwanted separation of bars, and actual bar not coming upto current date Windows 7 64bit Unwanted separation of bars, and actual bar not coming upto current date Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Quote:
1) Whenever I want to update a task, first I enter its % complete. Then I update the current date of the project and then I go to Tools>Tracking>Update Project. For the tasks that are 0% its no problem and MS project pushes the start date to current date. But for the tasks I entered a % already, it splits the task which I don’t want. How can I prevent this separation, for tasks that are already started, when I update the project date?
I'm guessing you are using the reschedule uncompleted tasks command to move remaining work forward to the status date? You can turn off the ability for Project to split tasks through Tools > Options, Schedule tab and deselect the option "split in progress tasks." However, that will leave remaining work in the past -- which sort of defeats the purpose of reschedule. Have you tried selecting 0 or 100% in the reschedule command?

Quote:
2) Also, I want it to bring the black progress bar in the blue bar up to the current date automatically, when I am doing all these. How can I do that
?

The black bar is percent complete -- if you are updating the percent complete the bar should be moving -- but you need to update the project. It will not assume because it is now Wednesday that you have progressed any. This is a manual update.
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Unwanted separation of bars, and actual bar not coming upto current date Appending the filename with the current date sheeand Word VBA 2 05-14-2012 05:18 AM
Unwanted separation of bars, and actual bar not coming upto current date Meaning of current date vs status date when saving baselines ketanco Project 1 02-08-2012 02:20 PM
updating status date and actual duration ketanco Project 5 01-27-2012 07:32 AM
Unwanted separation of bars, and actual bar not coming upto current date How to call current PC date and/or current PC year KIM SOLIS Excel 2 11-04-2011 06:09 PM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:55 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft