JulieS JulieS is offline assiging equipment as resource Windows 7 64bit assiging equipment as resource Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Yes, you cannot force two resources to work together on a single assignment. Each resource is scheduled on the task based upon his/her calendar.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
assiging equipment as resource how to enter equipment resources benson.wallace Project 5 03-15-2023 01:43 PM
Assiging more than one labor of the same type ketanco Project 5 06-08-2012 01:28 PM
assiging equipment as resource Managing equipment and person operating equipment ProfessorGilligan1 Project 1 04-12-2012 12:29 PM
assiging equipment as resource new name for outlook resource Rayat Outlook 1 07-05-2011 04:12 AM
Resource Calendars caz46 Project 0 02-12-2011 05:31 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:23 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft