Old 06-10-2012, 03:32 AM
JulieS JulieS is offline Windows 7 64bit Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Yes, you cannot force two resources to work together on a single assignment. Each resource is scheduled on the task based upon his/her calendar.