If you are referring to the printed legend at the bottom of the Gantt chart, the only method would be to create a new task bar named "holiday" or the like and then manually enter each holiday as a task in the project plan.
Normally, holidays are simply exceptions that are recorded in the project calendar. You can print exceptions in a report. Report menu > Reports, Overview, Working days. I hope this helps. Julie |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
How to Change/Edit the Bottom Task Area in Office Project 2007?
|
Rahmat_uk20 | Project | 3 | 06-07-2012 02:54 PM |
Let Office Object Library 14.0 work in Office 2007
|
tinfanide | Word VBA | 14 | 12-23-2011 02:43 PM |
| I can't figure out how to get Project 2010 to automatically rebalance my schedule | jackofnothing | Project | 0 | 10-23-2011 04:04 PM |
| Powerpoint project schedule | L J Keane | Project | 0 | 09-14-2010 01:24 AM |
Office 2007 Professional shipped from US, will it work on UK Windows PC's ?
|
OfficeDude | Office | 3 | 08-16-2009 02:11 PM |