![]() Assalam-o-Alaikum. I want to show Vacations in my Work Schedule / Plan at the Bottom of my Work Plan / Schedule in Office Project 2007. E.g. May 01, 2012 - Labor Day Aug 14, 1947 - Independence Day. Please help me in this regard. Thanks, Rahmatullah Khattak |
#2
|
|||
|
|||
![]()
If you are referring to the printed legend at the bottom of the Gantt chart, the only method would be to create a new task bar named "holiday" or the like and then manually enter each holiday as a task in the project plan.
Normally, holidays are simply exceptions that are recorded in the project calendar. You can print exceptions in a report. Report menu > Reports, Overview, Working days. I hope this helps. Julie |
#3
|
|||
|
|||
![]() Quote:
|
#4
|
|||
|
|||
![]()
You're welcome and thank you for the feedback.
|
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
Rahmat_uk20 | Project | 3 | 06-07-2012 02:54 PM |
![]() |
tinfanide | Word VBA | 14 | 12-23-2011 02:43 PM |
I can't figure out how to get Project 2010 to automatically rebalance my schedule | jackofnothing | Project | 0 | 10-23-2011 04:04 PM |
Powerpoint project schedule | L J Keane | Project | 0 | 09-14-2010 01:24 AM |
![]() |
OfficeDude | Office | 3 | 08-16-2009 02:11 PM |