![]() |
#2
|
|||
|
|||
![]()
Right click in the Gantt chart, choose Gridlines. Select the current date line and set the line style to the top choice (none). The line will still show as a a faint dotted line -- but you'll remove the orange line.
As a workaround when printing, temporarily change the current date in Project Information, to a date before the project start date. Julie |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
pstein | Word | 1 | 03-27-2012 03:20 AM |
![]() |
ketanco | Project | 1 | 03-16-2012 06:02 AM |
![]() |
ketanco | Project | 1 | 02-08-2012 02:20 PM |
updating status date and actual duration | ketanco | Project | 5 | 01-27-2012 07:32 AM |
![]() |
KIM SOLIS | Excel | 2 | 11-04-2011 06:09 PM |