JulieS JulieS is offline Current date vertical status line: How to turn off? Windows 7 64bit Current date vertical status line: How to turn off? Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Right click in the Gantt chart, choose Gridlines. Select the current date line and set the line style to the top choice (none). The line will still show as a a faint dotted line -- but you'll remove the orange line.

As a workaround when printing, temporarily change the current date in Project Information, to a date before the project start date.

Julie
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Current date vertical status line: How to turn off? How to get rid of the vertical line at the left side? pstein Word 1 03-27-2012 03:20 AM
Current date vertical status line: How to turn off? adjusting remaining work per status date ketanco Project 1 03-16-2012 06:02 AM
Current date vertical status line: How to turn off? Meaning of current date vs status date when saving baselines ketanco Project 1 02-08-2012 02:20 PM
updating status date and actual duration ketanco Project 5 01-27-2012 07:32 AM
Current date vertical status line: How to turn off? How to call current PC date and/or current PC year KIM SOLIS Excel 2 11-04-2011 06:09 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:46 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft