Work and Duration are not related until you assign resources.



If you enter 4 hours of work and 1 day duration, Project will not change the work if you go change duration unless you have resources assigned.

Project recalculates duration on effort driven tasks if you assign additional resources or unassign resources.


I do not enter work estimates until I assign resources -- and at that point it is that resource's work estimate for his/her work. If I need more people on the task, I am entering the next resources work estimate on assignment.

Julie
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
How to know the outstanding balance amount of a Loan? PRADEEPB270 Excel 1 01-07-2012 04:45 AM
amount of work Large amount of text as a form field. JustK Word 2 11-15-2011 11:17 AM
Sum required without consider the negative amount PRADEEPB270 Excel 2 08-22-2011 04:23 AM
Analysis of Amount based on following criterion. aligahk06 Excel 1 04-24-2010 10:34 AM
Convert Dollar amount to text GeorgeLawshe Word 0 03-07-2010 10:17 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:08 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft