![]() |
|
#10
|
|||
|
|||
|
Hi David,
Sorry for the delay in replying. I do now see what you are reporting. The level of accuracy is not to the minute in the team planner view. I also see that when I change the non-working time to something unusual (break from 12:08 to 1:08) the non-working time for that hour disappears from the team planner view. |
| Tags |
| team planner, timescale |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
duration vs actual start and finish dates
|
ketanco | Project | 1 | 12-14-2011 09:06 AM |
Task Start and End Dates
|
OTPM | Project | 2 | 12-04-2011 09:14 AM |
First To Finish Task Scheduling
|
Jody | Project | 6 | 09-23-2011 07:06 AM |
displaying start and finish times as absolute numbers instead of dates
|
benson.wallace | Project | 2 | 12-05-2010 07:22 AM |
| MS Project able to import actual start and or actual finish date from Excel? | mhacker | Project | 0 | 04-26-2010 11:29 AM |