Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 03-30-2012, 09:04 AM
JulieS JulieS is offline Team Planner-maintaining accuracy in task start and finish times Windows 7 64bit Team Planner-maintaining accuracy in task start and finish times Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Changing default start and end time to a 24-hour period is likely not wise. It should match your calendar. Are you using the 24-hours calendar to schedule your project?
Reply With Quote
  #2  
Old 04-04-2012, 01:46 AM
david_23 david_23 is offline Team Planner-maintaining accuracy in task start and finish times Windows 7 64bit Team Planner-maintaining accuracy in task start and finish times Office 2010 64bit
Novice
Team Planner-maintaining accuracy in task start and finish times
 
Join Date: Mar 2012
Posts: 7
david_23 is on a distinguished road
Default

Yes I am using the 24 hour calendar to schedule the calendar. Even though the task times now can be seen to start at their actual time. The shift start and end times are rounded up so this only partially solves the problem.
Reply With Quote
  #3  
Old 04-04-2012, 09:39 AM
JulieS JulieS is offline Team Planner-maintaining accuracy in task start and finish times Windows 7 64bit Team Planner-maintaining accuracy in task start and finish times Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi David,

I'm afraid I'm just not seeing what you see. Can you explain further? I'm guessing you are using durations in hours?
Reply With Quote
Reply

Tags
team planner, timescale



Similar Threads
Thread Thread Starter Forum Replies Last Post
Team Planner-maintaining accuracy in task start and finish times duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM
Team Planner-maintaining accuracy in task start and finish times Task Start and End Dates OTPM Project 2 12-04-2011 09:14 AM
Team Planner-maintaining accuracy in task start and finish times First To Finish Task Scheduling Jody Project 6 09-23-2011 07:06 AM
Team Planner-maintaining accuracy in task start and finish times displaying start and finish times as absolute numbers instead of dates benson.wallace Project 2 12-05-2010 07:22 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:54 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft