Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 03-30-2012, 05:33 AM
JulieS JulieS is offline Team Planner-maintaining accuracy in task start and finish times Windows 7 64bit Team Planner-maintaining accuracy in task start and finish times Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default


Hi David,

No sorry. When you zoom out, by definition you are losing accuracy. As an aside, unless you are working with manually scheduled tasks, entering start and finish dates/times is not usually the recommended method of using Project.
Reply With Quote
  #2  
Old 03-30-2012, 07:55 AM
david_23 david_23 is offline Team Planner-maintaining accuracy in task start and finish times Windows 7 64bit Team Planner-maintaining accuracy in task start and finish times Office 2010 64bit
Novice
Team Planner-maintaining accuracy in task start and finish times
 
Join Date: Mar 2012
Posts: 7
david_23 is on a distinguished road
Default

Thanks for the reply,
I have found out how to ensure the actual start of a task will be maintained regardless of what timescale is selected. Under File-Options-Schedule 'Default start time' and 'default end time' I had selected a 24hr period i.e. Start time = 00:00 and the end time 00:00. This was making the start time and end time round UP to the minimum time interval on the timeline. When i changed the end time to 23:59 the start and endtimes did not roundup anymore and stayed at their actual times on the timeline! Is this a bug with the software?
David
Reply With Quote
Reply

Tags
team planner, timescale

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Team Planner-maintaining accuracy in task start and finish times duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM
Team Planner-maintaining accuracy in task start and finish times Task Start and End Dates OTPM Project 2 12-04-2011 09:14 AM
Team Planner-maintaining accuracy in task start and finish times First To Finish Task Scheduling Jody Project 6 09-23-2011 07:06 AM
Team Planner-maintaining accuracy in task start and finish times displaying start and finish times as absolute numbers instead of dates benson.wallace Project 2 12-05-2010 07:22 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:27 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft