![]() |
#1
|
|||
|
|||
![]() Hello, I like to use milestones with fixed dates to track when other people/teams have promised a dependency, e.g. Test environment ready. A downside is that the constraint added by fixing the date causes the "Update Progress -> reschedule all tasks" feature that I use to carry forward uncompleted work on tasks after the status date to generates the warning "Project did not reschedule certain tasks because of a constraint date attached to them". Other than filtering out the milestones and then applying the update to selected tasks, is anyone aware of a way to get around this issue ? Thanks, Ben |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
rize1159 | Word | 1 | 11-20-2011 08:26 AM |
![]() |
P. Alkuin | Word | 2 | 03-15-2010 09:33 AM |
Section Breaks, maybe? | R20 | Word | 2 | 12-20-2009 06:35 PM |
Section Breaks | glenws | Word | 1 | 11-05-2009 02:10 PM |
Deleted Section Breaks Changes Page Breaks | Brantnshellie | Word | 0 | 02-01-2009 09:22 PM |