Hello,
I like to use milestones with fixed dates to track when other people/teams have promised a dependency, e.g. Test environment ready. A downside is that the constraint added by fixing the date causes the "Update Progress -> reschedule all tasks" feature that I use to carry forward uncompleted work on tasks after the status date to generates the warning "Project did not reschedule certain tasks because of a constraint date attached to them". Other than filtering out the milestones and then applying the update to selected tasks, is anyone aware of a way to get around this issue ? Thanks, Ben |
|
|