Updating the status date does not move tasks by itself. You need to run the Reschedule uncompleted tasks command -- which is going to split your task (which you did not like from a previous post) and move the remaining work to be scheduled as of the status date.
Then the remaining duration and the scheduled finish date should align. Julie |
|
![]() |
||||