Your calendar does not include weekends as working time -- other than setting Sunday, January 1 as a working day. Duration in project is Monday through Friday by default (working days) and I'm a bit confused by your statement:

"I want the dates to include the weekends. However noone works on the weekends."

There are 40 working days between Jan 1 and Feb 23. I have no idea what you mean by "adding up to 54 instead of 56." The tasks "Product Rationale" and "Product Specification" are running at the same time therefore the longest duration showing at the summary line is 40 days.



If you want to count all calendar days, alter your project calendar (Project > Change Working Time) to include Saturday and Sunday as working days.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
small office project Stevejd58 Office 4 06-09-2011 01:51 PM
Office Project on two monitors helpdeskguy Project 0 12-12-2010 08:09 PM
Hellp needed on office Project Newbie in Office Project wajebwahab Project 5 04-14-2010 01:40 PM
Help needed using the serial number date with sumifs - whole office is stumped FraserKitchell Excel 3 01-06-2010 12:24 PM
[Office]How to create project timeline similar to this? Coderedpl Project 0 09-11-2009 01:23 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:13 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft