Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 02-08-2012, 09:50 AM
ketanco ketanco is offline changing one activity in a baseline Windows 7 64bit changing one activity in a baseline Office 2007
Expert
changing one activity in a baseline
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default changing one activity in a baseline

Hi
After saving my baseline, I realized that there was an activity that was not in my schedule before. So I added that activity but now for my baseline columns, it is showing as n/a for that activity. Can I simply add dates and durations to that activitys baseline column so include it in the baseline I already saved or are there any negative consequences of doing this?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
updating a delayed activity ketanco Project 3 01-26-2012 01:47 PM
some work was complete at my baseline ketanco Project 1 01-25-2012 02:45 PM
changing one activity in a baseline change color of critical activity texts ketanco Project 3 01-05-2012 06:36 PM
changing one activity in a baseline Retrieve a baseline after it's been cleared fridos Project 2 05-11-2011 10:08 AM
changing one activity in a baseline Help with Interim Baseline Variance poyns Project 1 05-27-2010 10:59 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:37 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft