![]() |
|
#1
|
|||
|
|||
|
Hi After saving my baseline, I realized that there was an activity that was not in my schedule before. So I added that activity but now for my baseline columns, it is showing as n/a for that activity. Can I simply add dates and durations to that activitys baseline column so include it in the baseline I already saved or are there any negative consequences of doing this? |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| updating a delayed activity | ketanco | Project | 3 | 01-26-2012 01:47 PM |
| some work was complete at my baseline | ketanco | Project | 1 | 01-25-2012 02:45 PM |
change color of critical activity texts
|
ketanco | Project | 3 | 01-05-2012 06:36 PM |
Retrieve a baseline after it's been cleared
|
fridos | Project | 2 | 05-11-2011 10:08 AM |
Help with Interim Baseline Variance
|
poyns | Project | 1 | 05-27-2010 10:59 AM |