Quote:
Originally Posted by JulieS View Post
Select the task first. Then Tools > Tracking, Save Baseline for selected tasks.
i selected that task only and went where you described and it says "baseline has already been used on februyary 8 (the date i saved my baseline yesterday). are you sure you want to overwrite data in the baseline?"

so can i make this task part of baseline i saved yesterday? how?