Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 02-11-2012, 07:24 AM
JulieS JulieS is offline changing one activity in a baseline Windows 7 64bit changing one activity in a baseline Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The only way to add the task to the baseline is to re-baseline any summary task with the new task.


You may wish to save a new baseline (baseline1) to have different baselines for comparison.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
updating a delayed activity ketanco Project 3 01-26-2012 01:47 PM
some work was complete at my baseline ketanco Project 1 01-25-2012 02:45 PM
changing one activity in a baseline change color of critical activity texts ketanco Project 3 01-05-2012 06:36 PM
changing one activity in a baseline Retrieve a baseline after it's been cleared fridos Project 2 05-11-2011 10:08 AM
changing one activity in a baseline Help with Interim Baseline Variance poyns Project 1 05-27-2010 10:59 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:18 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft