Old 01-16-2012, 08:51 AM
ketanco ketanco is offline Adding or removing activities after basline Windows 7 64bit Adding or removing activities after basline Office 2007
Expert
Adding or removing activities after basline
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

Ok so in other words, you are saying that when we add or delete activities or change relations, the previous baseline inherently will not be apples to apples with the new actual sitation if we tried to use the same baseline, so you are saying we should make a new baseline in that case? I am just trying to understand if technically this is absolutely necessary or it is just a matter of preference. Which is technically the correct way I mean….
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Adding or removing activities after basline Removing tabs Taylor Word 10 11-28-2011 03:38 PM
Removing Custom XML Ulodesk Word 0 06-24-2011 09:01 AM
Link activities and milestones between projects (2003) jowian Project 0 11-25-2010 09:10 AM
OL 2010 Public Contact Activities ibstech Outlook 0 08-05-2010 10:25 AM
Removing All Formating basscarp Word 0 01-31-2010 05:49 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:50 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft