#1
|
|||
|
|||
|
Hi Julie, Thanx for your continued interest!Double click on Task ie task information. Advanced -> calendar-> Assign "Short week" Ceated new calendar. 25 hrs per week Not sure if I creatred a task calendar - it is described a base calendar. project 2010 - yes auto. |
|
#2
|
|||
|
|||
|
If you press F9, does the finish date change?
|
|
#3
|
|||
|
|||
|
Hello Julie,
F9 did not help. But I created a new Calendar (again) with the required working hours. And it now works just fine. I suspect that I had done something wrong when creating the calendar teh first time. Thanks for your help. Appreciated ;-) And I will remember F9, which google tells me, forces recalculation! |
|
#4
|
|||
|
|||
|
You're welcome. It sounds like things may have been off in the other calendar. I'm glad you have it sorted and thanks for the feedback.
Julie |
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Actual working hours per day | climbatron | Project | 2 | 12-17-2015 03:13 PM |
How to add hours together
|
PomDave | Excel | 3 | 09-05-2011 04:43 AM |
2007 Calendar - How do I show "working offsite" but available for phone meetings?
|
Stan | Outlook | 2 | 08-16-2011 09:30 AM |
Date and time calcs excluding non-working hours
|
mrsatchmo | Excel | 1 | 01-26-2011 08:50 AM |
| emailed outlook calendar not working | Tankerman | Outlook | 0 | 12-08-2010 10:36 AM |