Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 12-24-2011, 12:50 AM
ketanco ketanco is offline calculate multiple critical paths Windows 7 64bit calculate multiple critical paths Office 2007
Expert
calculate multiple critical paths
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default calculate multiple critical paths

i am trying to understand the meaning of multiple critical path. i obviously know the meaning of critical path but how can there be more than one? by definition isnt critical path only one? how come there are multiple?
Reply With Quote
  #2  
Old 12-24-2011, 01:02 PM
JulieS JulieS is offline calculate multiple critical paths Windows 7 64bit calculate multiple critical paths Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

see:
http://office.microsoft.com/en-us/pr...001226069.aspx

For each "path" without successors, the critical path is calculated for that path.
Reply With Quote
  #3  
Old 12-24-2011, 05:33 PM
ketanco ketanco is offline calculate multiple critical paths Windows 7 64bit calculate multiple critical paths Office 2007
Expert
calculate multiple critical paths
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

but i made sure in my schedule that everything other than the last task has a successor. so my project would not have multiple critical paths correct?
Reply With Quote
  #4  
Old 12-26-2011, 09:29 AM
JulieS JulieS is offline calculate multiple critical paths Windows 7 64bit calculate multiple critical paths Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You are correct.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
motion paths Cath5000 PowerPoint 0 07-29-2011 10:59 AM
calculate multiple critical paths Critical Path w/ 2 Calendars AndreT Project 6 07-27-2011 11:22 AM
Motion Paths with Rotation PBone PowerPoint 4 01-13-2011 11:59 AM
Motion paths and shrinking textbox Brin PowerPoint 0 01-12-2011 10:04 AM
HELP! Rebuilt box & IRM lock out of critical docs markcal Office 0 04-25-2010 11:45 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:38 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft