Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 12-14-2011, 09:06 AM
JulieS JulieS is offline duration vs actual start and finish dates Windows 7 64bit duration vs actual start and finish dates Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The question mark is an indication of "estimated" duration. If you allow Project to calculate the duration (as in question one) the question mark shows. If you manually enter a duration (question two) the question mark disappears.



You can control the display of the question mark Project 2007 through Tools > Options, scheduling tab and unchecking "Show that tasks have estimated durations" and "New tasks have estimated duration".

In Project 2010 it is controlled through File > Options > Schedule and the option "Show that scheduled tasks have estimated durations" and "New Scheduled tasks have estimated durations." So, for the question marks appearing or not, that is an option for each product.

To question 2 - you entered a duration, so the "estimated" no longer applies. The Actual finish disappeared because you increased duration. So the task is no longer complete (% complete is less than 100). The change in duration add the increase to "Remaining Duration". Apply the tracking table to see most of the tracking fields.

To question 3 - you entered a duration which was shorter than the actual duration. Project assumed the new duration is correct, the adjusted the "Actual Duration" to the new lower value and recalculated the Actual Finish date.

I hope this helps.
Julie
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
duration vs actual start and finish dates Calendar without actual dates parnol01 Project 1 12-16-2015 09:30 AM
duration vs actual start and finish dates Task Start and End Dates OTPM Project 2 12-04-2011 09:14 AM
duration vs actual start and finish dates displaying start and finish times as absolute numbers instead of dates benson.wallace Project 2 12-05-2010 07:22 AM
duration vs actual start and finish dates Setting Drop Dead Start Dates greenboard Project 2 06-14-2010 08:12 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:18 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft