![]() |
#1
|
|||
|
|||
![]()
Hi
I am using Project 2010 and cannot understand why if a task starts at 0900hrs on a Monday and is a five day task, the finish date is showing as 0900hrs the following Monday rather than 1700 hrs on the previous Friday! I am using an eight hour day calendar. Can anyone help. Tony(OTPM) |
#2
|
|||
|
|||
![]()
Hi, I have exactly the same problem. Have you figured how to solve it?
|
#3
|
|||
|
|||
![]()
Hi anarita,
What is the definition of a "day" in File > Options, Schedule? There are three places you need to ensure things are in synch: **Project calendar - the default working time in the Standard Calendar is 08:00 - 12:00 and 13:00 to 17:00. If your working time is something other than that -- you need to modify the calendar for every working day through the Change Working Time command on the Project tab. **Default start, default end, hours per day and hours per week setting in File > Options, Schedule. **Resource calendar definitions - each resource has a calendar which is based upon another calendar. If the resource's calendar is different, this can also cause task dates and times to shift. My guess is that you have a task which starts at 09:00 on Monday set a duration of 5 days (which equals 40 hours). Add 40 hours to 09:00 on Monday and you get 09:00 on the following Monday. You have started 1 hour into the working day (08:00 - 17:00) so the one hour you've missed on Monday morning has to be continued to the following Monday morning from 08:00 to 09:00. I hope this helps. Julie |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
start-stop month dates in calendar | madison320 | Project | 0 | 06-24-2011 08:15 AM |
![]() |
Daria11 | Word VBA | 1 | 06-08-2011 06:54 PM |
![]() |
benson.wallace | Project | 2 | 12-05-2010 07:22 AM |
how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |
![]() |
greenboard | Project | 2 | 06-14-2010 08:12 AM |