Hi I am using Project 2010 and cannot understand why if a task starts at 0900hrs on a Monday and is a five day task, the finish date is showing as 0900hrs the following Monday rather than 1700 hrs on the previous Friday! I am using an eight hour day calendar. Can anyone help. Tony(OTPM) |
|
|