Constraints in MS Project
 
Join Date: Aug 2011
Posts: 18
Antares is on a distinguished road
Default

I have another question:
If I have two tasks - first is with "Start as late as possible" and the second is "as soon as possible" and they are linked with FS relation.
The project completion date is somewhere far away.
So in this case which constarint dominates?
"as late as possible" tends to push first task to the end (and consequently the linked second task is also pushed, but why "as soon as possible" of second task cant resist this push)...
Well my questions - which can be stronger ?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
How to protect project? Prabhakar Project 1 05-17-2011 07:39 AM
Need for MS Project 2007 aligahk06 Project 0 07-03-2010 10:09 AM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM
Different % complete in Project Center & View a Project mikaelbelchior Project 1 01-25-2006 12:56 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:38 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft