I have another question:
If I have two tasks - first is with "Start as late as possible" and the second is "as soon as possible" and they are linked with FS relation. The project completion date is somewhere far away. So in this case which constarint dominates? "as late as possible" tends to push first task to the end (and consequently the linked second task is also pushed, but why "as soon as possible" of second task cant resist this push)... Well my questions - which can be stronger ? |
|
![]() |
||||