JulieS JulieS is offline Constraints in MS Project Windows 7 64bit Constraints in MS Project Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi Antares,
No, sorry. A single task can only have one constraint, either FNLT or SNET. You can work around with milestones linked with constraints.

Also, leveling will not "fit this task in this interval" it will only delay tasks based upon resource overallocation, the priority of the task, and the ability to split a task.

I hope this helps.
Julie
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
How to protect project? Prabhakar Project 1 05-17-2011 07:39 AM
Need for MS Project 2007 aligahk06 Project 0 07-03-2010 10:09 AM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM
Different % complete in Project Center & View a Project mikaelbelchior Project 1 01-25-2006 12:56 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:38 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft