BobBridges BobBridges is offline Calculating turnaround times in excel Windows 7 64bit Calculating turnaround times in excel Office 2010 32bit
Expert
 
Join Date: May 2013
Location: USA
Posts: 700
BobBridges has a spectacular aura aboutBobBridges has a spectacular aura about
Default

Swooshy, I'm not sure I follow. Suppose you figure out an easy way to calculate dates. 2013-10-28 13:39 to 2013-11-11 11:51, that's 13.9250 days; then you consult that manual tab of dates you want to omit, say one Saturday and two Sundays, and you come up with 10.9250 days. Is that a useful result? I don't see how.

It seems to me that if you don't want to count every calendar day as one day—which is reasonable enough—then you must define for yourself what you do count as a day.

For example, how will 8 hours work for you? If a person works 16 hours on Wednesday, will you count that as two days? If he works four 10-hour days and then goes home Friday, is that five days?

If so, then it's not so hard; you count up the hours a person worked, divide by 8 and presto!, a day count. But if not that, then what exactly?

Or maybe that's what you're asking us, for some advice on how to define a "day"?
Reply With Quote
  #2  
Old 11-14-2013, 04:37 AM
Swooshy Swooshy is offline Calculating turnaround times in excel Windows 7 64bit Calculating turnaround times in excel Office 2010 64bit
Novice
Calculating turnaround times in excel
 
Join Date: Nov 2013
Posts: 7
Swooshy is on a distinguished road
Default

Quote:
Originally Posted by BobBridges View Post
Swooshy, I'm not sure I follow. Suppose you figure out an easy way to calculate dates. 2013-10-28 13:39 to 2013-11-11 11:51, that's 13.9250 days; then you consult that manual tab of dates you want to omit, say one Saturday and two Sundays, and you come up with 10.9250 days. Is that a useful result? I don't see how.

It seems to me that if you don't want to count every calendar day as one day—which is reasonable enough—then you must define for yourself what you do count as a day.

For example, how will 8 hours work for you? If a person works 16 hours on Wednesday, will you count that as two days? If he works four 10-hour days and then goes home Friday, is that five days?

If so, then it's not so hard; you count up the hours a person worked, divide by 8 and presto!, a day count. But if not that, then what exactly?

Or maybe that's what you're asking us, for some advice on how to define a "day"?
the idea is to calculate turn around times which would typically just be the normal working week so weekends excluded however the industry demands that certain weekend days be worked particularly coming up to EOQ so the network days does not accurately fit the needs.

A day is typically 1 set of 24 hours due to the fact that the item may be worked upon by various groups around the globe. this is why a simple hours calculation is not readily appropriate in this regards as the department may be working beyond normal working hours on occasions
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Calculating turnaround times in excel Need a formula to calculate turnaround time Rockitman31 Excel 9 09-07-2015 09:41 AM
Calculating Profits? MarkL Project 1 06-12-2012 07:19 AM
Calculating turnaround times in excel calculating duration ketanco Project 5 12-15-2011 07:15 PM
Calculating turnaround times in excel Calculating dates Daria11 Word VBA 1 06-08-2011 06:54 PM
calculating points and division in excel edward masoya Excel 1 05-09-2011 06:31 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:21 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft