Sorry, no. Project is designed to plot tasks (surveys in your case) against time. One possible structure is to have the Properties as summary tasks with the specific surveys listed as subtasks. As it doesn't sound like there is any relationship between the surveys (they are no dependent upon one another) you might consider using Manually Scheduled tasks (assuming you have Projec 2010 or 2013).

I'd be curious as to why the client wants you to use Project? This does not, strictly speaking, sound like the classic use.