I want to show cum scheduled work to the status date for each task in a table column to help my cost control person understand the BCWS values that MSP calculates. I understand that this is displayed in the timescaled task usage field. Therefore it must be calculated internally by summing the timescaled scheduled work to the status date, but it is not offered as a custom field in MSP 2003. It appears that it is in later versions, and I am wondering if there is a formula I could use to customize a field to display in a column.