MSProject 2013 - making two12 hr shifts/day
View Single Post
07-29-2014, 05:38 PM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
You create calendars in Project > Change working time > Create new calendar. See:
http://office.microsoft.com/en-us/pr...102809468.aspx
for details on changing the work weeks to something other than 8-12, 1-5.
JulieS