Thread: [Solved] MSP 2010 Resource Allocation
View Single Post
 
Old 05-24-2014, 12:41 PM
JulieS JulieS is offline Windows 7 64bit Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

By default, resources are assigned at their maximum units to the task. So a two day duration task and a resource assigned at 100% (default value) will result in 16 hours of work. If you want to allow the resource two days (duration) to accomplish 3 hours of work, you'll need to initially set the task type as Fixed Duration. Enter the 2 days duration and then assign the resource with 3 hours of work. Project will calculate the Peak units necessary to spread the 3 hours of work out over 2 days. Then you may want to set the task type back to either Fixed Units or Fixed work.
Reply With Quote