Thread: [Solved] Timeline date format
View Single Post
 
Old 04-19-2013, 06:26 AM
JulieS JulieS is offline Windows 7 64bit Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm not sure if you are talking about the Timeline view or the timescale in the Gantt chart view.

  • Timeline view - use the Date Format button on the Timeline Tools Format ribbon. Select W4/4 format.
  • Timescale in Gantt view - right click in the timescale, select Timescale and change the label as needed.