Thread
: [Solved]
Baseline query
View Single Post
01-24-2013, 10:48 AM
JulieS
Windows 7 64bit
Office 2010 32bit
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
in Project 2010:
Project tab > Set Baseline > Set baseline.
click Set Interim Plan
Copy Baseline
Intro: Baseline 1
You can then set the calculation of variance through File > Options, Advanced.
JulieS
View Public Profile
Find all posts by JulieS