Automatic Units Scaling
Hello All,
I am relatively new to MS Project, looking for a solution to the following problem. Suppose I have two tasks and one resource.
Initially I would like to have R work on A & B simultaneously; 50% on task A and 50% on task B. After two days task A will have been completed, and task B will have 50% remaining. Does MS Project provide the capability such that R will automatically start to dedicate 100% of his "units" to task B, once task A has been completed? Many thanks for any hint or tips in advance! |
Tags |
resource leveling, units |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Place Metric units in parenthesis behind English units | JaapOnFire | Word VBA | 6 | 06-03-2014 12:50 PM |
Scaling font size when scaling canvas in Word 2010 | j_d | Drawing and Graphics | 0 | 05-10-2013 01:18 AM |
Scaling a poster down | Jvic28 | Word | 4 | 04-04-2012 02:05 PM |
Automatic resouce assignment of remaining unallocated units | philk | Project | 0 | 05-04-2011 04:57 PM |
Scaling A4 to A3 | Jonnyv | Publisher | 1 | 04-21-2006 06:15 AM |