#1
|
|||
|
|||
|
okay
I will try that and let you know how I make out thanks for all of the help so far |
|
#2
|
|||
|
|||
|
I have the fileds entered into the task in the order that you seggested. do I need to do a baseline save in orer for the info in these fields to stick?
|
|
#3
|
|||
|
|||
|
Kimberly
I tried your suggestion and I could not get the actuals to agree with what I was putting in. the example I used I have the calandar set to a 6 hour work day. baseline start 11/01/10 baseline finish 11/03/10 baseline work 18 actual start 11/01/10 act finish 11/02/10 actual hours 9 if I enter the act start of 11/01/10 and the act finish of 11/02/10 and the act work at 9, the act work changes to 12 and the % comp is 100. if I change the act work back to 9, the act finish goes to NA and the % comp goes to 75. I am beginning to think that project can't do estimates verus actual tracking. |
|
|
|