No! Ideally you should create a baseline right before you start working the project, after all the tasks are entered, etc.
You just set a baseline one time... again, this is done between the time you create the plan and start working the plan... right before you enter any actuals.

Setting one now though would be muich better than not one at all.
Reply With Quote
Reply



Other Forums: Access Forums

All times are GMT -7. The time now is 07:41 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft