MS Project Start Dates not matching the Status Date
 
Join Date: Nov 2011
Posts: 3
sjodom is on a distinguished road
Default MS Project Start Dates not matching the Status Date

Hello,



I am working with a schedule that is placing all "Finish No Later Than" constraint tasks to the project start date, not the status date, which would make more sense to me. Currently, the tasks do not have any actuals, nor constraint dates. But I would like to see these tasks not so far in the past. Any suggestions?

Schedule options currently set:
New tasks: Start on Current Date
Calc. mode: Automatic
Move end of completed parts after status date back to status date (off)
Move start of remaining parts before status date forward to status date (on)

I am relatively new to MS Project, so any assistance is appreciated. Thank you!
Reply With Quote
  #2  
Old 11-15-2011, 01:24 PM
sjodom sjodom is offline MS Project Start Dates not matching the Status Date Windows 7 32bit MS Project Start Dates not matching the Status Date Office 2007
Novice
MS Project Start Dates not matching the Status Date
 
Join Date: Nov 2011
Posts: 3
sjodom is on a distinguished road
Default

Nobody has any suggestions?
Reply With Quote
  #3  
Old 12-02-2011, 08:19 AM
sjodom sjodom is offline MS Project Start Dates not matching the Status Date Windows 7 32bit MS Project Start Dates not matching the Status Date Office 2007
Novice
MS Project Start Dates not matching the Status Date
 
Join Date: Nov 2011
Posts: 3
sjodom is on a distinguished road
Default

Awesome guys. Thanks for the suggestions. Another site, here I come.
Reply With Quote
  #4  
Old 12-04-2011, 08:45 AM
JulieS JulieS is offline MS Project Start Dates not matching the Status Date Windows 7 64bit MS Project Start Dates not matching the Status Date Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi sjodom,
Did you find help on another site? If not, post back and I'll try to assist. How are you adding the constraints? Usually if you add constraints you specify the constraint date.

Are you scheduling the project from the start date or the finish date? (Check Project > Project Information)

Julie
Reply With Quote
Reply

Tags
ms project, start date, status date

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
MS Project Start Dates not matching the Status Date Task Start and End Dates OTPM Project 2 12-04-2011 09:14 AM
start-stop month dates in calendar madison320 Project 0 06-24-2011 08:15 AM
MS Project Start Dates not matching the Status Date Project start date steve138 Project 4 05-20-2011 04:55 AM
MS Project Start Dates not matching the Status Date Setting Drop Dead Start Dates greenboard Project 2 06-14-2010 08:12 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:16 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft