Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 10-23-2011, 04:04 PM
jackofnothing jackofnothing is offline I can't figure out how to get Project 2010 to automatically rebalance my schedule Windows 7 64bit I can't figure out how to get Project 2010 to automatically rebalance my schedule Office 2010 64bit
Novice
I can't figure out how to get Project 2010 to automatically rebalance my schedule
 
Join Date: Oct 2011
Posts: 1
jackofnothing is on a distinguished road
Default I can't figure out how to get Project 2010 to automatically rebalance my schedule

Hi Everyone,



I am a complete Project 2010 newbie, and would love to get some assistance. I've been doing a ton of Googling and still can't find an answer.

Hypothetically, let's assume my Project plan has two tasks, and let's assume I assign resource = ME to both tasks where the second task starts after the first task is completed.

If for some reason I actually start my first task a month late, I would like Project 2010 to recalibrate itself such that I can easily continue on with my plan. The way it currently works, is if I have several tasks and I don't get to a few days or weeks late, the tasks are still scheduled to start at the same days in the past. I wish it could rebalance itself so I can easily continue the project from where I left off (and as a result it would recalculate the start dates for any incomplete tasks to start either today or after (not in the past).

I hope I'm making sense - any help would be more than greatly appreciated - Thank you!

Rebecca
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Can Word automatically update figure numbers? gib65 Word 7 02-22-2013 05:52 AM
I can't figure out how to get Project 2010 to automatically rebalance my schedule MS Project 2010 Durations not working seanpears99 Project 1 10-07-2011 07:28 AM
Microsoft Project 2010 automation without VS Fil Project 0 09-15-2011 10:17 AM
Powerpoint project schedule L J Keane Project 0 09-14-2010 01:24 AM
Bar chart in Project 2010. aligahk06 Project 0 07-04-2010 07:37 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:54 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft