Work calculated differently for two seemingly identical tasks
Hi, I would appreciate some help.
I have two tasks, both with duration 5 days and a single resource with 80% allocation. One task shows Work of 4 days, which is what I expect. The second task shows Work of 1.6 days. Both tasks are fixed duration, with Effort Driven deselected. They have the same start date. I don't understand the difference in Work. Where does the 1.6 days come from? Any ideas what I am doing wrong? Any help appreciated... Thanks STEVE |
|