JR_12 JR_12 is offline Ignore Resource Work Times Windows 7 32bit Ignore Resource Work Times Office 2007
Novice
Ignore Resource Work Times
 
Join Date: Oct 2011
Posts: 2
JR_12 is on a distinguished road
Default Ignore Resource Work Times

Hello All,



I am trying to put a schedule together, but I'm having a little trouble. Right now I'm trying to schedule various resources (employees) during their shifts; however, part of their operations include running a machine over night where they do not have to monitor it; however since they only have a 10 hour work day the task continues longer than it should since it's assuming it can't be done outside of that time frame.

I was wondering if there a way I could make that particular tasks ignore the work times so that it will reflect an accurate schedule?

Also, I apologize if it's not very clear so please let me know if you need clarification.

Essentially, all I am trying to do is make it so a task ignores the resource's availability and continues to run. It would be ok also if I could assign the specific task a 24 hour schedule so it's never delayed and just runs continually.

Thank you in advance for your help.
Reply With Quote
  #2  
Old 12-04-2011, 04:00 PM
sullied sullied is offline Ignore Resource Work Times Windows 7 64bit Ignore Resource Work Times Office 2010 64bit
Novice
 
Join Date: Dec 2011
Posts: 3
sullied is on a distinguished road
Default

Using an 'elapsed duration' will help you with this. To do this, I'll provide you with an example. Let's say you have a task that requires a glue to cure for 14 hours, but you want it to continue into non-working time. Simply make the task duration as 14 ehrs, rather than 14 hrs. Adding the 'e' in front of the time units will make it so that it ignores the work schedule.

Hope that helps!
Reply With Quote
  #3  
Old 12-05-2011, 06:35 PM
JulieS JulieS is offline Ignore Resource Work Times Windows 7 64bit Ignore Resource Work Times Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Quote:
Originally Posted by JR_12 View Post
Hello All,


Essentially, all I am trying to do is make it so a task ignores the resource's availability and continues to run. It would be ok also if I could assign the specific task a 24 hour schedule so it's never delayed and just runs continually.

Thank you in advance for your help.
Another option, in addition to sullied suggestion to use elapsed duration, is to assign the built-in 24-hours calendar as a task calendar. Double click on the task and on the Advanced tab set the 24-hour hours calendar as the task calendar.

I hope this helps.

Julie
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Meeting times different texaminn Outlook 0 05-19-2011 02:05 PM
Ignore Resource Work Times Help with checking available times Deepy Excel 1 02-14-2011 05:06 PM
Ignore Resource Work Times Can I do calculations with times? cubsfan_1 Excel 1 01-14-2010 06:55 PM
Ignore Resource Work Times Copying page 1 800 times echomakr Word 1 09-11-2009 08:00 AM
Ignore Resource Work Times Ignore a section in grammar checker stlsailor Word 1 07-28-2009 12:45 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:17 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft