Hello,
I have a question, issue:
I have several people in my team, they are partialy (20%-100%) assigned to my project. So they spend not all the time they have on my tasks. Lets say per task 5%. So they do have paralel tasks and deadlines, for example one person has to deliver 2 finished tasks in one day. (not a issue ist about 2 hours for him to do so) he still has other things to do the day then just my project, for example customer communication.
Never the less having this in place is quite a pain in Project, but my situation is even wors, I have to report mandays on my project, but not the real based on hours the people acctually spend on the project, but since all of them are from one division and since the division planning is build up so that all people are from planning assigned to the project, I have to report all the days they work even for few hours as full days.
Any way how to do so?
Reply With Quote
  #2  
Old 10-06-2011, 03:29 AM
OTPM OTPM is offline Reporting ManDays on people not fully assigned to the Project Windows 7 32bit Reporting ManDays on people not fully assigned to the Project Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi
The Resource Usage report will give you this information.
Good luck.
Tony
Reply With Quote
  #3  
Old 10-06-2011, 04:10 AM
Imagios Imagios is offline Reporting ManDays on people not fully assigned to the Project Windows 7 64bit Reporting ManDays on people not fully assigned to the Project Office 2010 64bit
Novice
Reporting ManDays on people not fully assigned to the Project
 
Join Date: Oct 2011
Posts: 18
Imagios is on a distinguished road
Default

Hello,
may be I do something wrong, but if I go there I see the hours/days they accualy have to work not the days their are assigned to...
for example if someone is assigned for two hours I need a report showing is was working two hours as well as a report that he was assigned for one day. Its for internal cost reporting...
Reply With Quote
  #4  
Old 10-06-2011, 04:23 AM
OTPM OTPM is offline Reporting ManDays on people not fully assigned to the Project Windows 7 32bit Reporting ManDays on people not fully assigned to the Project Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi
It sounds like you are not using MS Project correctly. You can record Scheduled Activity and Actual Activity against each resource together with dates and times.
What are you actually looking for?
Tony
Reply With Quote
  #5  
Old 10-06-2011, 04:37 AM
Imagios Imagios is offline Reporting ManDays on people not fully assigned to the Project Windows 7 64bit Reporting ManDays on people not fully assigned to the Project Office 2010 64bit
Novice
Reporting ManDays on people not fully assigned to the Project
 
Join Date: Oct 2011
Posts: 18
Imagios is on a distinguished road
Default

OK may be I express my self wrong...

One thing is and that is what I need to see how much time one accualy spends on the project, that I can find in the team view...

Second thing is for internal reasons all the people contributing to the project are reported as fully assigned. That means if his task start at the 1.11. and ends on 15.11. even he is assined only for 5% and works on the task few hours, I need a report showing that he worked two weeks, in this case 10 Mandays.
Reply With Quote
  #6  
Old 10-06-2011, 10:00 AM
OTPM OTPM is offline Reporting ManDays on people not fully assigned to the Project Windows 7 32bit Reporting ManDays on people not fully assigned to the Project Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi
In that case, irrespective of how long they ACTUALLY spend doing the tasks you can assign then as 100% on the task for the given period. The you can use the resource usage report to show how long each person is assigned to the project.
OR
You can create a custom view in Project with the information you need to show. Then export the data to Excel and change the start and Finish columns just to show the dates and not the times if you still want Project to just show the ACTUAL hours spent on the project.
Hope this helps.
Tony
Reply With Quote
  #7  
Old 10-07-2011, 04:29 AM
Imagios Imagios is offline Reporting ManDays on people not fully assigned to the Project Windows 7 64bit Reporting ManDays on people not fully assigned to the Project Office 2010 64bit
Novice
Reporting ManDays on people not fully assigned to the Project
 
Join Date: Oct 2011
Posts: 18
Imagios is on a distinguished road
Default

I tried the first solution, but since the people have more tasks in the same period assigned them, to put them as 100% per task has a result of people shown as overloaded in the resources diagram, I thought there is a simpler solution in Project for that...
Im sure Im not the only one having the issue that people assigned to projects do accutualy as well other things than to work only on the project... but this is more a topic of accurate planning and as well about a conflict of theory and praxis
Reply With Quote
  #8  
Old 10-07-2011, 04:47 AM
OTPM OTPM is offline Reporting ManDays on people not fully assigned to the Project Windows 7 32bit Reporting ManDays on people not fully assigned to the Project Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi
Project will only report on planned and actual assignment durations. It cannot report anything in between.
As I suggested earlier you can export assignment information to Excel and then in nthe Start and Finish columns in Excel you can change the date format so that it reports on the day only and not the time.
Hope this helps.
Good luck.
Tony (OTPM)
Reply With Quote
  #9  
Old 10-10-2011, 04:18 AM
Imagios Imagios is offline Reporting ManDays on people not fully assigned to the Project Windows 7 64bit Reporting ManDays on people not fully assigned to the Project Office 2010 64bit
Novice
Reporting ManDays on people not fully assigned to the Project
 
Join Date: Oct 2011
Posts: 18
Imagios is on a distinguished road
Default

OK seems to be the only solution

one more question, how would you handle tasks that the assigned person have to do within two weeks, but its accualy a day work, you dont care when he does it, but he has to be done till a certain day, is there a way how to have the start of the task and end as two weeks but the task him self is a days work?
Or ist the best way to make it a two weeks task and assign the resource as for example 5%?
Reply With Quote
  #10  
Old 10-10-2011, 04:36 AM
OTPM OTPM is offline Reporting ManDays on people not fully assigned to the Project Windows 7 32bit Reporting ManDays on people not fully assigned to the Project Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi
What you can do is actually record a task of say 10 elapsed days (10ed).
Then you record only the actual time the resource works on the task.
Hope this helps.
Good luck.
Tony
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Reporting ManDays on people not fully assigned to the Project Converting Powerpoint into Fully Accessable PDFs KCD123 PowerPoint 4 09-28-2011 10:03 AM
Hyperlink assigned sounds do not play Starscream PowerPoint 0 03-08-2011 02:14 PM
Resource Overallocation Reporting Mutso Project 0 11-05-2010 12:27 PM
Reporting ManDays on people not fully assigned to the Project Outlook 2007 Not Fully Closing LabanM Outlook 1 09-28-2010 02:27 PM
Project Reporting vickib1 Project 0 09-08-2010 03:11 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:06 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft