seanpears99 seanpears99 is offline MS Project 2010 Durations not working Windows 7 64bit MS Project 2010 Durations not working Office 2007
Novice
MS Project 2010 Durations not working
 
Join Date: Oct 2011
Posts: 12
seanpears99 is on a distinguished road
Default MS Project 2010 Durations not working

Hi everyone

When I use 2003 and enter the start and end date for an activity it automatically calculates the duration for me (I know you shouldnt be constraining, just wondering how to get 2010 to operate like 2003)

When I enter the start and end dates in 2010, the duration remains at 1d? unconfirmed.

Is there a setting which I turn on to calculate the durations?

Thanks


Sean
Reply With Quote
  #2  
Old 10-07-2011, 07:28 AM
OTPM OTPM is offline MS Project 2010 Durations not working Windows 7 32bit MS Project 2010 Durations not working Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi
Have you set your tasks to be auto scheduled? If not this may be the issue.
Good luck.
Tony
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Milestone durations fraserm Project 4 01-13-2012 08:43 AM
Microsoft Project 2010 automation without VS Fil Project 0 09-15-2011 10:17 AM
How can I use persian (solar) calendar in ms project 2010? mammadkoma Project 0 11-13-2010 06:01 AM
Calculate slide durations for song hb2010 PowerPoint 1 10-19-2010 06:41 AM
Bar chart in Project 2010. aligahk06 Project 0 07-04-2010 07:37 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:48 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft