Hi,


I Just want to know difference between "poll task precedence & sharer task precedence" while working with resource pool.

Regards,
Himanshu
Reply With Quote
  #2  
Old 09-13-2011, 03:07 AM
OTPM OTPM is offline MS Project Doubt Windows 7 32bit MS Project Doubt Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi Himanshu
I am not sure what you mean by poll task precedence and sharer task precedence.
If you are looking at a Resource View then the resource name will include all the tasks assigned to that resource indented under their name.
Hope this helps.
Tony(OTPM)
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
MS Project Doubt cctshimanshu Project 2 09-13-2011 02:17 AM
Ms Project Doubt cctshimanshu Project 3 09-09-2011 01:44 AM
MS Project Doubt cctshimanshu Project 7 09-07-2011 08:03 AM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:47 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft