  #1  
Old 09-06-2011, 09:45 PM
cctshimanshu cctshimanshu is offline Ms Project Doubt Windows XP Ms Project Doubt Office 2007
Novice
Ms Project Doubt
 
Join Date: Sep 2011
Location: New Delhi, India
Posts: 9
cctshimanshu is on a distinguished road
Default Ms Project Doubt


Please explain the use & difference among bar roll up. Milestone date & mile stone rollup? With Example.
Reply With Quote
  #2  
Old 09-07-2011, 12:55 AM
OTPM OTPM is offline Ms Project Doubt Windows 7 32bit Ms Project Doubt Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi
If I understand you correctly, a Bar rollup is all sub tasks rolled up into the Summary Task, this will then give you the earliest start and latest finish for all sub tasks contained in the Summary Task.
Milestone Tasks are simply indicators in a plan that advise when a certain point or task(s) are completed with a plan, there is not really such a process as Milestone Bar rollup.
Hope this helps.
Tony(OTPM)
Reply With Quote
  #3  
Old 09-08-2011, 11:36 PM
cctshimanshu cctshimanshu is offline Ms Project Doubt Windows XP Ms Project Doubt Office 2007
Novice
Ms Project Doubt
 
Join Date: Sep 2011
Location: New Delhi, India
Posts: 9
cctshimanshu is on a distinguished road
Default

Dear Tony

Thanks for your reply!

I understand how to use above option but still I did not understand concept behind these. Why we are using these option. Please give some example also.

Regards,
Himanshu
Reply With Quote
  #4  
Old 09-09-2011, 01:44 AM
OTPM OTPM is offline Ms Project Doubt Windows 7 32bit Ms Project Doubt Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi
In my opinion there is no suich thing as a "Milestone Roll-up". An individual Milestone indicates you have reached a pre-determined point in the project.

A Summary bar roll-up is where you collapse all sub-tasks to the summary bar so the plan just shows Summary bars with the earliest start and latest finish for all the tasks sitting underneath that Summary task. This is normally used to provide Management with a summary progress view of the project without them having to go through the whole plan.

Hope this helps.
Tony(OTPM)
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
MS Project Doubt cctshimanshu Project 7 09-07-2011 08:03 AM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM
Need some basic help on Project NewToProject Project 0 04-06-2008 07:03 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM
Different % complete in Project Center & View a Project mikaelbelchior Project 1 01-25-2006 12:56 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:25 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft