Please explain the use & difference among bar roll up. Milestone date & mile stone rollup? With Example.
|
#2
|
|||
|
|||
![]()
Hi
If I understand you correctly, a Bar rollup is all sub tasks rolled up into the Summary Task, this will then give you the earliest start and latest finish for all sub tasks contained in the Summary Task. Milestone Tasks are simply indicators in a plan that advise when a certain point or task(s) are completed with a plan, there is not really such a process as Milestone Bar rollup. Hope this helps. Tony(OTPM) |
#3
|
|||
|
|||
![]()
Dear Tony
Thanks for your reply! I understand how to use above option but still I did not understand concept behind these. Why we are using these option. Please give some example also. Regards, Himanshu |
#4
|
|||
|
|||
![]()
Hi
In my opinion there is no suich thing as a "Milestone Roll-up". An individual Milestone indicates you have reached a pre-determined point in the project. A Summary bar roll-up is where you collapse all sub-tasks to the summary bar so the plan just shows Summary bars with the earliest start and latest finish for all the tasks sitting underneath that Summary task. This is normally used to provide Management with a summary progress view of the project without them having to go through the whole plan. Hope this helps. Tony(OTPM) |
![]() |
Thread Tools | |
Display Modes | |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
MS Project Doubt | cctshimanshu | Project | 7 | 09-07-2011 08:03 AM |
Connectivity issue of Project Professional with Project Server | kashif | Project | 0 | 03-27-2009 06:37 AM |
Need some basic help on Project | NewToProject | Project | 0 | 04-06-2008 07:03 AM |
Error 9571 when opening Project Server from Project Pro | mona | Project | 0 | 04-24-2007 07:50 AM |
Different % complete in Project Center & View a Project | mikaelbelchior | Project | 1 | 01-25-2006 12:56 AM |